Dynamics
Dynamic IP-Tunnel project Work Breakdown Structure $Revision: 1.4 $ State approved
Date 04-Dec-1998 Author Tom Weckström
Review date 10-Dec-1998 Reviewed by Jouni Malinen
Approval date 10-Dec-1998 Approved by Jouni Malinen
$Id: dynamicsWBS.html,v 1.4 1998/12/09 23:58:50 jkmaline Exp $


Introduction

This document describes the Dynamic IP-Tunnel project project Work Breakdown Structure (WBS). The project has been divided into six main phases described in the project plan document. The WBS describes the main activities and effort estimates. Each main activity shall have one responsible person. The activities are further divided into tasks (or todos) that are reported in the project progress reports. Each phase is divided into specific task related A.b/c codes. The A part of the code defines the phase of the project. Each phase is divided into main operational areas defined with  b level codes. Some of the b level codes are further divided into several c level codes. The c level codes are very close to the actual tasks of the phase. Tasks are practically same as todos. Strictly interpreted a todo is one sort of a task. The schedule of the phases and the deadlines inside the phases are defined in the project Gantt chart. There is no scheduling for the lower level activities, which are constrained by the phase deadlines.
 
 
DYNAMICS-project's a.b/c-codes
 
a.b/c  Description Estimate Responsible
 
1  Project planning phase (PS)  248,00   
1.1  Lectures  56,00 
1.2  Studying  27,00 
1.3  Meetings  94,00 
1.3/1  Team meetings  58,00 
1.3/2  Customer meetings  36,00 
1.4  Project management  11,00  TWE
1.5  Documentation, Project plan  31,00  TWE 
1.6  Documentation, Requirements spec.  24,00  TWE 
1.7  Documentation, Progress report  2,00  TWE
1.8  Equipment analysis  3,00  JMA 
2  Definition phase (MÄ)  270,00   
2.1  Meetings  72,00 
2.1/1  Team meetings  36,00 
2.1/2  Customer meetings  12,00 
2.1/3  Course inspection meetings  12,00 
2.1/4  Team inspection meetings  12,00 
2.2  Documentation  45,00 
2.2/1  Project plan  10,00 
TWE
2.2/2  Requirements spec.  4,00  TWE
2.2/3  Progress report  5,00  TWE
2.2/4  Functional definition  20,00  BAN
2.2/5  Other documents  6,00 
2.3  Architecture definition  14,00  BAN
2.5  Defining the functnlty of the elements  10,00  BAN
2.6  Definition of the inter operability  9,00  BAN
2.7  Support tools definition  4,00  JHA
2.8  Definition of the API  6,00  JHA
2.9  Security definition  4,00  KMU
2.10  Project management  12,00  TWE
2.11  Equipment administration  8,00 
2.11/1  Hardware installation  3,00  JMA
2.11/2  Software installation  5,00  JMA
2.12  Tik-76.115 lectures  18,00  *
2.13  Studying the project field  26,00  *
2.14  WWW-administration  4,00  JMA
2.15  Project planning  3,00  TWE
2.16  Reviews  6,00  *
2.17  Other activities  10,00  *
2.18  Definition of the protocol  14,00  BAN
3  Design phase (SU)  271,00 
3.1  Meetings  90,00 
3.1/1  Team meetings  50,00 
3.1/2  Customer meetings  12,00 
3.1/3  Course inspection meetings  10,00 
3.1/4  Team inspection meetings  18,00 
3.2  Documentation  46,00 
3.2/1  Project plan  5,00  TWE
3.2/2  Technical design definition  18,00  BAN
3.2/3  Progress report  5,00  TWE
3.2/4  Functional definition  5,00  BAN
3.2/5  Testing plan SU  5,00  KMU
3.2/6  Other documents  8,00 
3.3  Architecture design  5,00  BAN
3.4  Protocol design  12,00  BAN
3.5  Mobile Node design  7,00  JHA
3.6  Foreign Agent design  10,00  DFO
3.7  Home Agent design  10,00  BAN
3.8  Support tools design  6,00  JHA
3.9  Testability design  10,00 
3.9/1  Test module design  4,00  KMU
3.9/2  Oranization of the testing  3,00  KMU
3.9/3  Test case design  3,00  KMU
3.10  Alpha prototype design  8,00  DFO
3.11  Demonstration planning  4,00  DFO
3.12  Tik-76.115 lectures  10,00 
3.13  Studying the project field  18,00 
3.14  WWW-administration  6,00  JMA
3.15  Project management  10,00  TWE
3.16  Document reviews  9,00 
3.18  Equipment administration  4,00 
4  Prototype 1 phase (P1)  270,00 
4.1  Meetings  60,00 
4.1/1  Team meetings  27,00  *
4.1/2  Customer meetings  9,00  *
4.1/3  Course inspection meetings  10,00  *
4.1/4  Team inspection meetings  14,00  *
4.2  Documentation  42,00 
4.2/1  Project plan  2,00  TWE
4.2/2  Technical design definition  10,00  BAN
4.2/3  Progress report  5,00  TWE
4.2/4  Functional definition  4,00  BAN
4.2/5  Testing report P1  9,00  KMU
4.2/6  User manuals  9,00  JHA
4.2/7  Other documents  3,00  JHA
4.3  Mobile Node implementation  11,00  JHA
4.4  Foreign Agent implementation  14,00  DFO
4.5  Home Agent implementation  13,00  BAN
4.7  Test environment establishment  15,00  KMU
4.7/1  Test module implementation  9,00  *
4.7/2  Test case organization  6,00  KMU
4.8  Support tools implementation  10,00  JHA
4.9  Testing  10,00  *
4.10  Demonstration planning  9,00  JMA
4.11  Studying the project field  17,00  *
4.12  WWW-administration  5,00  JMA
4.13  Project management  8,00  TWE
4.14  Document reviews  15,00  *
4.15  Equipment administration  5,00  JMA
4.16  Other activities  3,00  *
4.17  Team Communications  18,00  *
4.18  Implementation of general modules  15,00  *
5  Prototype 2 phase (P2)  0,00 
5.1  Meetings  0,00 
5.1/1  Team meetings  0,00 
5.1/2  Customer meetings  0,00 
5.1/3  Course inspection meetings  0,00 
5.1/4  Team inspection meetings  0,00 
5.2  Documentation  0,00 
5.2/1  Project plan  0,00 
5.2/2  Technical design definition  0,00 
5.2/3  Progress report  0,00 
5.2/4  Functional definition  0,00 
5.2/5  Testing report P2  0,00 
5.2/6  User manuals  0,00 
5.7  Test environment establishment  0,00 
5.7/1  Test module implementation  0,00 
5.7/2  Test case organization  0,00 
5.8  Testing  0,00 
5.10  Demonstration planning  0,00 
5.11  Studying the project field  0,00 
5.12  WWW-administration  0,00 
5.13  Project management  0,00 
5.14  Document reviews  0,00 
5.15  Equipment administration  0,00 
5.16  Other activities  0,00 
6  Delivery phase (LU)  0,00 
6.1  Meetings  0,00 
6.1/1  Team meetings  0,00 
6.1/2  Customer meetings  0,00 
6.1/3  Course inspection meetings  0,00 
6.1/4  Team inspection meetings  0,00 
6.2  Documentation  0,00 
6.2/1  Project completion report  0,00 
6.2/2  Technical design definition  0,00 
6.2/3  Progress report  0,00 
6.2/4  Testing report LU  0,00 
6.2/5  User manuals  0,00 
6.7  Test environment establishment  0,00 
6.7/1  Test module implementation  0,00 
6.7/2  Test case organization  0,00 
6.8  Testing [KMU]  0,00 
6.9  Product delivery preparations  0,00 
6.10  Final demonstration planning  0,00 
6.11  Studying the project field  0,00 
6.12  WWW-administration  0,00 
6.13  Project management  0,00 
6.14  Document reviews  0,00 
6.15  Equipment administration  0,00 
6.16  Other activities  0,00 
 